132/33kV Reinforcement Project - Shrewsbury, Shropshire
Introduction
Western Power Distribution (WPD) has recognised the increasing load at Shrewsbury GSP and it is predicted to exceed its n-1 firm capacity of 117MVA by the end of DR5. Therefore they are installing a third 132/33kV transformer, auxiliary transformer and associated apparatus to accommodate the growth
Wootton & Wootton were contracted to provide a turnkey package for the project management, excavation & reinstatement, installation of 132 & 33kV cables. This included the installation of temporary work platforms, all terminations and cable sealing ends, Sheath testing and 132kV pressure testing upon completion
The works were successfully completed on budget and ahead of schedule.
Scope of Works.
To excavate backfill & reinstate 240m of track to accommodate 132 & 33Kv cables
Installation of 3 x direct laid (160m) 132kV 400mm Cu, XLPE, Pb sheath, CWS, & MDPE outer sheath Cables between the new GT4 and the new S/S structures within the AIS compound
Installation of 9 x (45m) 33kV 630mm Cu XLPE CWS Cables between the new GT4 and the existing switchgear
Installation of 3 x (30m) 33kV 630mm Cu XLPE CWS Cables between the new GT4 and the Auxillary transformer
Installation of 1 x (15m) 33kV 630mm Cu XLPE CWS Cables between the new GT4 Auxiliary transformer to the LNER
To install 6 x 132kV Prysmian sealing ends
To install 6 x link boxes including bonding lead installation and connections
To install 16 x 630mm 33Kv 400 series Euromold terminations onto the 132/33Kv transformer and associated auxiliary transformer
To supply & install 1 x 33Kv Outdoor termination onto the LNER
To supply & install scaffold structures at each 132kV CSE position
To drill all transformer gland plates and supply & install all cable management & cleating requirements
Carry out Pressure test, Tan Delta test and Partial Discharge mapping of the 132kV cable system upon completion
To supply full time project management and monitored security system for the duration of the project, authorised standby supervision where required, verify cable system design and supply the client with as laid drawings and appropriate handover paperwork.
BACK CONTACT US