66kV AIS Substation Installation - Northwick, Gloucestershire
Introduction
Northwick Estates in Gloucestershire gained permission to construct their own anaerobic digestion system to produce electricity to feed back into the grid.
Wootton & Wootton were contracted to project manage, build & commission a 66KV AIS Substation. Our work comprised of the following:
Scope of Works.
Full time on site project management for the duration of the project
The installation of 1 x Steel Sealing End Structure
The installation of 2 x Steel 66kV Disconnector structures
The installation of 1 x steel 66kV CB structures
The installation of 3 x steel 66kV Post Insulator structures
The installation of 3 x steel 66kV VT structures
The installation of 1 x 66kV CBs
The installation of 2 x 66kV Dis-connector / earth switches
The installation of 1 x set 66kV surge arrestors
The installation of 6 x 66kV Post Insulators
The installation of 3 x 66kV VTs
The Installation of 5 sets 3 phase bus bars
The Installation of 2 sets 3 phase droppers
The Installation of Relay Panel for 66kV Bay
The Installation of AVC Panel for 25MVA 66/11kV Transformer
The Installation of SCADA Panel
The Installation of Interface Wall Box
The Installation of Battery chargers
The installation of 1 x 66KV underground 66KV XLPE Cct
The installation of 6 x 66KV Outdoor Raychem terminations
To Carry out an AC VLF Pressure test
Summary.
Despite difficult site conditions the project was delivered on time and on budget
BACK CONTACT US