33kV Gas Generation Site - Manchester
Wootton & Wootton undertook works to install all 33kV cables, 33kV jointing and testing for the installation of 7 Transformers and the DNO connections on a new Gas Generation Site in Manachester.
Works were carried out for a new client to their high standards and satisfaction.
- Prove, Clean & Rope Ducts
- Install 1100m of 33kV 240mm Al XLPE comprising 7 individual Transformer circuits
- Install 3 x 33kV 400mm XLPE Al cables between customer switchgear & DNO switchroom
- Supply & Install 2 x sets 400mm 33kV sixe 3 Pfisterer inner cone plug in terminations
- Supply & Install 1 x set 400mm 33kV Euromold Separable Connectors
- Install 3 x 33kV Pre-Made VT LEads
- Supply & Instal 14 x 240mm 33kV Euromold separable connectors
- Supply & Install cabale management systems
- Design, manufacture & install switchgear vermin plates
- Carry out all sheath testing, insulation resistance tests and final pressure testing
- Seal all ducts on completion